Ask a business owner what their biggest problem is, and there is a good chance you will hear one word “communication”.

When I keep asking, that word almost always turns into something more specific. Information is getting lost in project handoffs, the moments when a piece of work passes from one person or group to the next.

That is good news. “Communication” is too big to fix. A single handoff is small enough to fix this week.

“Communication” Is Usually Five Smaller Problems

Earlier this year I sat down with two business owners, separately, and asked what their biggest problem was. Both said communication. When I dug in, it broke into five relationships: the internal team, the customer, the supplier, the designer and the toolmaker. Five places where information moves from one set of hands to another, and five places where it can be dropped, misread or delayed.

A moulding program is about the clearest example of handoffs you will find. A part starts as the customer’s idea, goes to a designer, then to a toolmaker who cuts the mould (the steel tool that shapes the plastic), then to the shop floor that runs it. Here is what I have seen go wrong at each of those five handoffs, and what helped.

The Five Project Handoffs on a Moulding Program

1. Customer to your team

Early in my career I designed automotive headlamps. On a run of prototype programs for one automaker, the math data (the 3D surface files that describe the part) had to travel from the customer to us and then on to the tool shops. The customer’s data came with its own format and its own requirements, so I wrote those requirements down in one document the whole design group could check. Before this document existed we had no record of what was being sent or received to who and when and at what revision level.

Later, on my own programs, I made a habit of sending the customer preliminary drawings to confirm the concept, the appearance and the fit before going further. The customer saw it before we committed, not after.

Compare that with the defroster grille program I have written about before. Nobody asked the customer what surface finish they would accept. We assumed, and the parts were rejected at approval sampling.

The question for this handoff: what does the customer need to confirm before we commit?

2. Designer to toolmaker

At the same company, what counted as a finished design ready for the tool shop depended on who was releasing it. So we wrote down the minimum content required at each stage before a design could be released for tooling. The tool shop received the same complete package every time, instead of whatever the designer had on hand that day.

The question: is there a written definition of “ready” for this handoff?

3. Toolmaker back to you

Handoffs run both ways. On an offshore tooling job I have written about before, the supplier sent two good sample parts. There were 24 inserts (the replaceable pieces of the mould that each form one feature of the part) across three moulds. Those two parts came from inserts cut before the cutting bit went dull. The other 22 had a small undercut that locked the parts in the mould. The handoff told us everything was fine because it only showed us part of the picture.

At another moulder, I set up teleconferencing with our tool shops, with remote access so our engineers could run the shop’s software during meetings. Both sides looked at the same screen instead of describing it to each other.

The question: what exactly was checked, and what was not?

4. Supplier paperwork

On a 2022 launch, a shipping company used the wrong delivery terms on some documents: DAP instead of DDP. Those codes decide who handles the delivery and the import duties. A one-letter difference cut our seven-day buffer for getting parts to the equipment builder down to three days. We still met the schedule, because the buffer was there to absorb it. This one didnt get caught until it was chewing up my time buffer. I had parts going from Germany to USA equipment builder DAP. I had to find a customs agent that could interpret what was happening because it was out of our control one country to another. I dont care what it costs, please look after your own paper work.

The question: who checks the paperwork before it leaves, not after it arrives? Is it in front of the correct people? are the right questions being asked. 

5. Inside your own team

The trickiest handoffs are often between groups under the same roof. On that same launch, a piece of equipment run by a different group had been planned without a matching event, a trial where real parts are run through new equipment to tune it. I had built extra parts into my own plan for the unexpected, and those parts were used to get that welder matched. It worked out, but because of spare parts, not because the two plans talked to each other.

The smoothest internal handoff I remember was on a park and signal lamp that sat above the headlamp on a full-size pickup, so appearance was everything. I talked early and often with the assembly and moulding departments, and the prototype and production tools kicked off smoothly. At the same company, we gave the quality and moulding groups direct access to the design data library, so they were not waiting for someone to send them files.

The question: does the next group see the same information we see?

What This Means for Your Business

You may never build a mould, but your business has the same five project handoffs. The customer hands you a request, a quote or a change. Whoever sells or estimates the job hands it to whoever does the work. Suppliers hand you materials and paperwork. Your own people pass jobs between the office and the field, or from one shift to the next. Most businesses never map their handoffs, so nobody notices where the leaks are.

When an owner tells me the problem is communication, I have learned that the first answer is rarely the real problem. The real problem is usually one specific handoff where information drops. Fix that one, and “communication” improves without anyone holding a meeting about it.

It is rarely a knowledge problem, it is usually a time problem. In every story above, somebody knew what was needed. The knowledge just did not travel, because nobody had time to write it down or check it at the handoff. The fix is not smarter people. It is making each handoff simple enough that it gets done on a busy day.

Fix Your Handoffs One at a Time

You do not need to fix all five project handoffs at once. Pick one job from the last month that went sideways, trace it back, and ask these questions:

  • Where did this job change hands?
  • What did the person receiving it need that they did not get?
  • Was there a written definition of “done” for that handoff?
  • Who checked it before it moved on?

Then write a five-line checklist for that one handoff and tape it where the handoff happens. A sheet of paper on the wall is fine. If it works, add the next one. Every working automated system started as a working manual one, and the same goes for clean hand project offs.

A Second Set of Eyes

I spent 35 years in injection moulding, in part design, tool design and program management, and I hold a PMP. Most of what I do now is help owners find the one place information keeps dropping, as a project manager when you need one.

If your team keeps saying “communication” and you would like help finding which of your project handoffs is the real problem,let’s talk.

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes:

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>